The short answer is: Specify aluminum covers for the roof hatch and then specify paint for aluminum for field painting. (All within the spec and perfectly coordinated.)
The long answer is:
I agree with most of what has been said, but we should be cautious: Ideally, we should only specify what’s indicated, but that’s an ideal and not practical. We are not in the business of creating perfect documents and should not allow our profession to be judged by such a standard. (That may be overstated a bit.) Rather, there is a process that needs to be followed to get things right and that process includes the contractor during construction, including RFI’s and modifications.
We use drafts in a very similar fashion as Dave mentioned. And we do have a meeting for a “page by page” as he describes, (nearly always anyway). But the assumption is that someone at the meeting knows the answers at that meeting time, for example, whether aluminum is on the project or not. This of course applies to any other item being questioned. Often, we are given a qualified yes, maybe we have aluminum, now; leave it in.
Also, we cannot allow ourselves to specify only what’s there and nothing more. Drawings do not show everything; it’s not a matter of physical items/quantities shown on drawings and quality requirements specified. Many items are not shown at all: Fasteners are not shown, hardware is not shown, shop finishes and galvanizing. [I deleted a long list here for simplicity.] The point is we need to “see” with specifer eyes and specify everything that is required for what is shown. There are decisions for these items and they need to be discussed. The page-by-page review should accomplish most of this. We are not always present during a page-by-page review, but we receive the markups.
Complementary? Not always. Sometimes the only place to identify an item is in the spec, and it may not be shown on the Drawings at all. Elevator pit ladders can be specified and identified as one per pit. In these cases, if it’s in the spec it IS in the contract documents.
Besides using the coordination review with the specifier and the design team, the AIA A201 requires a review of the contractor. If read carefully, the contractor who notes an item as shown but not specified, or conversely, specified but not shown, I read that the contractor is obligated to report it. (There’s no obligation to find errors, but the contractor is obligated to report known items that affect constructability, such as a product without a spec).
I’ve not heard of this A201 requirement getting someone off a hook after construction, but I have seen this process work well in finding missing items that need specs before serious consequences occur during construction. The system can work.
I remember in the old days, when we wrote with pens, “When in doubt leave it out”. Now we should say, “When in doubt, ask”.
If this is too much just stay with the short answer.