When I learned about CDT, the instructor started off by saying “There is the right way, the wrong way, and the CSI way. This class and the exams are about the CSI way.” When I starting teaching CDT and certifications, I had a similar approach; but over the years I have adopted the opinion that the CSI way is the right way. After all, it is based on sound interpretation of governing documents, contracts, and so forth.
But here’s the thing: Steven Bruneel is correct. Once you know the right way, you are free to deviate from it because you (presumably) have the knowledge and experience to understand the risks and implications of deviating. I’d suggest that toilet seat probably deserves it own spec section and shouldnt be in toilet accessories, but otherwise, I agree with him.
As relating to risk, Brian’s use of BSD language to locate backing board in non-wet areas is not a big deal because installers understand what needs to be done on most jobs, so it ends up getting done correctly. But you properly need to define all the terms to make it work. Is the back splash area between the base and wall cabinets a wet area? Is the bathroom wall outside the shower surround a wet area? What happens when you have a vertical wall with a small horizontal area, like a window stool? What happens when your designer wants a slightly inclined wall is it vertical or horizontal, or something else?
Do you use ASTM C840 or a GA standard to locate control joints in gypsum walls? Not a bad time saver for most jobs, but that relies on the craftsmanship and aesthetic sense of the installer. What about in that big assembly space with all the doors where the 30 on center rule doesnt quite work out visually? You can start listing exceptions like put control joints at doorways, but its better to draw the wall in elevation (which you have done anyway, probably) and show the joints.
I only raise these issues to raise awareness, and Im probably preaching to the choir on this forum. Using standardized spec language to locate work is a more acceptable risk in smaller firms, where everyone understands what the spec says, and where everyone (or someone) is aware that an out of the ordinary situation calls for a re-evaluation of what the spec says. In larger firms, its less acceptable and riskier because there are more cracks for things to drop into, and far few people know what is typically in the spec.
Locating work in the spec instead of on the drawings can be an acceptable deviation from standard specification practice, but there is no substitution for making sure everyone on the team understands the standards. That’s why so many of us preach the value of the CDT for everyone on the team, and the certifications for the key people doing the specs and CCA.