I will state that getting the lists (correctly) even as an internal specifier, is not easy. Our own group is trained about not changing titles willy nilly, but consultants are something else.
The drawing lists they send over are ‘lies’ for want of a better word. Not only are the titles not likely what they say they are, but they may have not included drawings that they list, and they may have added drawings that they did not list.
Even for the list on the drawing cover sheet, we have our end trained to not finialize this sheet until they have laid an eyeball on the actual drawings when they are sent to us. Project managers also tell the consultants that they cannot change a drawing title without first telling us about the change.
All of that said, we DO issue a list of drawing in the project manual. I would say that about 80% of our owner/developers we work with require or request it. And if not directly them, then its their lenders wanting a document that can be used to describe the drawings and one that describes the project manual, including dates of issue, etc.
So, we do this on every project, required or not. It is likly we will get a request for such at some point anyway, and its nice not to have to kluge something together at the last minute when the Owner says he needs something sent to the lender’s lawyers “in the next 15 minutes”.
Also, the lenders/lawyers, they are very picky that the titles be exactly as they actually appear. So, we have a nice drill here in the office where we assure that it is as it should be.
This means that the list of drawings is the last document I get before I send the package off to print. It comes to me in a generic format that all I need to do is ‘copy paste’ into word and it adopts the format of the block of text. The project managers/architects are putting it in directly to their CAD files. When it is in, they extract it out and email it to me and I take about 15 minutes and finalize it.
All very quick, however, as I said above, it does not happen until we lay eyeballs on the drawings from the consultants. Often this has meant that the project manual goes to print overnight on the day the drawings are issued - so it is lagging 1 day behind.
And every time - yes, 100% of the time - no matter how trustworthy, no matter how long we have been working with them, every consultant’s lists that they have sent in advance has been different from the drawings as they actually are issued.
And since it is never nice to have addendum 1 be the reissue of the drawing cover sheet and the project manual list of drawings, once a project manager is burned, it never happens again. We wait.
Yes, cases do arise where the owner absolutely needs to have the project manaul on a certain date. In that case he is told in advance that the list of drawings will not be included and what is on the cover sheet will most likely be incorrect. Then we follow up with the list of drawings as addendum number 1.
In doing this, we have a utility for the document. As I implied above, it lists the drawing number, title, and its date of issue (or revision). It does not track every revision date, just lists the current date.
What we do when we issue an addendum or amendment where we issue drawings is the project architect takes the list and hilights those drawings beind revised. I then change the date to state “Revised xxx” showing the new date. In the short index of the addendum, rather than list the individual drawings, it states that drawings listed as ‘revised xxx’ in the list of drawings are revised and reissued herewith. Similar for new drawings.
So the Contractor, us, our CA staff and the owner and everyone else, gets a new list of drawings each time - and it shows the current date for every drawing in the set.
And yes - sometimes we get calls from consultants that state, “hey, I thought I issued drawing zzz in that addendum, what happened to it”. Which means, he did not carry it on his list and did not print it himself either. And the obvious corallary, "why is drawing zzz revised, we did not change anything (when actually, they really did - or they did but did not intend to issue it with the current addendum).
I can see the logic for the independent consultant - its of no value to you. I would never include it. Furnished as a separate document perhaps, but not officially in. Let the architect create it. He may not need it, and it is nothing but heartache and delays to your publishing deadline.
But for Architects, often it is necessary, depending on your client - and you can turn it to good use internally.
William