We are perfoming a building flushout to meet this credit but did not go for EQ3.1 As part of EQ3.2 the template requires you to upload the IAQ Management Plan. Is the same IAQ plan in EQ3.1 or one for just pre-occupancy (not during construction)?
We are perfoming a building flushout to meet this credit but did not go for EQ3.1 As part of EQ3.2 the template requires you to upload the IAQ Management Plan. Is the same IAQ plan in EQ3.1 or one for just pre-occupancy (not during construction)?