Mark:
I’m not sure what you’re try to get at with your question, but the design team (architect and its consultants) must address the client’s needs in their design. In essence, if the architect does not coordinate and review the work products of its consultants, the consultant can, without doing anything that I mentioned above, specify something contrary to the owner’s and architect’s desires–thus, where there is conflict, the more specific will prevail. What I am proposing just minimizes the potential RFIs and maybe disputes resulting from such conflicts in the documents, but does not relieve the A/E from providing a coordinated set of documents.
Like the general conditions, not every provision works for every situation; thus, if a general provision in Division 01 does not suit a particular specification section, then there are means of accommodating that specific requirement.
For example, lets say in Division 01 it is specified that where samples are requested in the technical sections three samples are required to be submitted. One sample will be retained by the architect and two returned to the contractor. However, the owner has requested that it would like a copy of one particular sample, too. So, in that specific section the architect states four samples of that item are required and two will be retained by the architect.
It’s that simple. There is no need for the architect to obtain from its consultants what all the exceptions are for a project to incorporate them into Division 01–that would be a coordination nightmare.
To alleviate what might be conceived as a conflict in the documents, the minor adjustments to Division 01 by individual sections can be addressed in Division 01. Using MasterSpec as an example, in Section 01 10 00 “Summary” there is a paragraph that states the following:
“Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.”
This can be modified with a subparagraph as follows:
“Where a more specific requirement is provided within an individual section, that specific requirement takes precedence over the Division 01 general requirement for that individual section only.”
Obviously, this would apply to all provisions in the specifications. But if you wanted to narrow it down to just alternate requirements for submittal requirements, then the Division 01 submittals section can state that specific submittal requirements in individual sections take precedence over the general requirements in the Division 01 submittals section.