Typically everyone of my spec sections starts with some form of the following wording under header, Related Documents: “Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section.”
On a project being constructed in Trinidad, the final construction agreement no longer references AIA Documents (I am not privy to the actual document). Therefore the GC has asked that this wording be deleted from each spec section.
My concern is that the specifications were developed based on language in the General Conditions. The architect has advised that neither the GC nor the Architect will be referencing any AIA document. This job has been going on since 2006 when AIA General Conditions were accepted, now they are not.
I will be formulating a disclaimer statement to add to the Additional Services Agreement and to each actual spec sections to cover what I expect will be future confusion on administering the Contract. Am I overly concerned? Anyone want to offer a recommendation for a disclaimer statement to include in each spec section?