Ron this is happening in epidemic proportions as I have preached on this forum in the past. BTW, not being a member of AIA, I am not able to post on their forum, ironically the architect who posted the query on 3/18 is a past client at a different firm, whom I have had discussion with…I will reach out to John thru linkedin.
IMHO, Contractors in Florida have succeeded in convincing Owners/Developers that omitting specifications from the Contract Documents will save them significant $$$. Of course this means leaving the quality of construction up to the Contractor who only cares about the amount of $$$ in their pocket. This is happening mostly on condominium work where in this cycle there are billions of dollars of construction moving forward without specifications, I have seen long time clients who always use specifications decline to use them.
Even on projects where specifications are included I have seen back room deals where Developers have deleted specifications from the Construction Contract without telling the Architect which places the Architect in a serious position since the drawings were prepared with specifications in place.
Even Architects are agreeing to this approach, if the Developer won’t pay for the specifications, the Architects are not willing to take the fees out of their contracts.
Phil, greed and fear of litigation also plays a part, One of the ways a Condo litigator can prove negligence by an Architect is to prove that the specifications are not coordinated with the drawings. A good specifier will ensure this is part of their service, but Architects must do their part by instructing their PM’s to read the specifications. This has not happened, Architects use many excuses for this, they assume the specifier has a crystal ball and can predict changes to the documents.
Phil appealing to the State licensing board is a total waste of time when it comes to this approach. I have a great deal of respect for DPBR, but they will not get involved in this, primarily because the Architects in Florida have given up the fight…for now.
I expect that 5-7 years from now when defects and shoddy construction starts surfacing the Architects will start realizing they have been duped. It will be too late than.
Fortunately I have a few clients who are not following the pack, these are the ones who have already experienced litigation and realize the important of specifications.
Wayne, I prepare short form specifications on some projects, mostly multi-family low to mid rise rental projects, but I refuse to do so on Condo work.
I know of at least one 70+ story condo tower under construction in SFL without specifications, I was asked to prepare specs for the project by both the Architect and Developer, however they insisted on Outline specs limited to a few paragraphs per section, I refused to do that, I gave the Architect a list of other specifiers in the state and nationally, but I guess no one took the offer, as there are no specs on file for the project.