(shameless plug)
In Construction Specifications Writing, Principles and Procedures(5th Ed.), I addressed a chapter on shortform specifications. I also included an example Division 01 - General Requirements. I based the requirements on the use of AIA contract documents. I only included requirements that I think are most important for an uncomplicated, light construction project. And tried, tried to not get into being too directive about issues such as temporary construction and a lot of administrative procedures.
It was difficult because I come from a position where I think a comprehensive Division 01 is very important, especially on public projects.
Drawing on what I learned from Herman Hoyer (read his series on shortform specs elsewhere on 4specs.com), I abandoned the 3-PART format (please don’t tell the Spec Police). For “work results” Sections in other Divisions, I am moving toward the development of prototype shortform specs which rely on product data and work results information being put on the Drawings as much as feasible. That is, use schedules and notes on the Drawings and minimize text in the Specifications. Keep information about the qualitative aspects of products in the Specifications and identify products and their locations in the funny papers … I mean, on the Drawings.
One good example of this is Structural Notes which are required by many plancheck authorities to be on the Structural Drawings. Rather than duplicate information, I prefer to refer to specific locations in the Drawings, such as in Structural Notes, for product information for “structural” elements. Considering the topic of structural steel, I put in the specifications only requirements that are not strictly “structural.” Otherwise, shortform specs should refer to the Structural Notes. Examples to keep in the specifications are requirements for Architecturally Exposed Steel (AESS) and primers on the steel.
For finish materials and door hardware, the schedules on Drawings may need have added information so that bidders and constructors know clearly what is intended and who is the basis-of-design manufacturer, supplier or fabricator. And a lot of specification text can be eliminated by having the Drawings refer to things such as TCNA Hanbook installation methods and materials. The SMACNA Manual is another good “reference” document for Drawing details that eliminate a lot of specification text.
I cheat in shortform specs by using phrases such as “match Architect’s sample”, “match existing” and “as [noted] [indicated] on the Drawings,” rather than writing a whole bunch of stuff that says essentially the same thing, or maybe contradictory things.
Shortform specs should not attempt get involved with all the potential topics found in SectionFormat. SectionFormat needs to be locked away when writing shortform specs. The challenge needs to be to radically reduce text in the specifications without hindering bidding and construction … and rendering quality assurance meaningless too.
The primary limitation of shortform specs … they are best suited for simple, light construction project of limited scope … needs to be kept in mind. I’ve written multi-volume Project Manuals. I fear I may be cavalier in taking on shortform specs, but I think it’s an oppportunity to have contact with a major portion of the design community who could use some education in product evaluation & selection and construction specifications writing. Remember, it’s going to be them who will operate the BIMco Spec-O-Matic machine and give the spec writer the results to fix-up for hard bidding and construction.