Since the Contractor keeps its own RFI log, not entering gbogush RFIs gin the RFI logh may be less useful that it first appears. The Contractor will still claim the RFI count as accurate.
I try to “quantify” all RFIs as they are being answered and include our categorization of the RFI in our response. This creates a contemporaneous record of the RFIs, and, if we are honest about issues that are “the AEs”, provides veracity for the record.
In categorizing the RFIs we categorize the"reason" the RFI was submitted, and the “type” of response. Some examples are as follows:
RFI Request Reason: This is the reason the contractor stated, or our best interpretation thereof. Some Contractors seem to always list “potential change” or something similar as a reason.
Agency Generated: Governing agency code interpretations, newly enacted codes or policies being enforced.
Change Request: C.M./Contractor requested change or substitution. We usually reject these and require the submission of a “Substitution Request” form, with complete backup.
Clarification: Request for clarification.
Non-conformance: Concerning work by the Contractor that is non-conforming (for example, a wall was installed incorrectly. The contractor may ask that we accept the “as-built” location.)
Owner Generated: Owner requested change or substitution.
Unforeseen: Unforeseen or unexpected existing conditions (for example, soil conditions are different, or the condition of an exist building [or component thereof] is different than
indicated in the record documents.)
RFI Response Type (How we categorize the RFI response)
Agency Generated: Related to question or issue raised by AHJ (Authority Having Jurisdiction). Unforeseen agency code interpretations, newly enacted codes or policies being enforced, etc.
Change to Documents: Question / Response generated a change to the Contract Documents (CDs) that was a result of a design refinement (other than issues generated by AHJ, contractor, existing or unanticipated condition, owner or nonconformance should use the appropriate Response Type). If the response is considered a change to the CDs we should so indicate.
Clarification/Interpretation: Response is consistent with the intent of and reasonably inferable from the Contract Documents.
CM/Contractor generated: C.M./Contractor requested change or substitution.
Existing/unanticipated condition: Unforeseen or unexpected existing conditions (for example, soil conditions are different, or the condition of an exist building [or component thereof] is different than indicated in the record documents.
Information In Documents: The information requested was in the current Contract Documents (for example, if the contractor says there is no detail for a condition and we can point to
an existing detail).
Non-conformance: Concerning work by the Contractor that is non-conforming (for example, a wall was installed incorrectly. The contractor may ask that we accept the “as-built” condition.)
We also return RFIs ananswered if they are incomplete or unclear.
If we “categorize” the RFIs consistantly and fairly, we can usually show that the percentage of RFIs that are due to “errors and omissions” are low. We can also show any “patterns” in the contractors RFIs (sending RFIs that are incomplete, RFIs that have answers on the CDs, RFIs that are requests to cheapen details, etc.