This is an extension of a previous thread from May 2005 which can be reviewed at: http://discus.4specs.com/discus/messages/23/1644.html
I really havent found any discussion on what happens when there are discrepancies between documents other than Drawings and Specifications, like between the Agreement (Contract) and the Drawings, or the Conditions. A201 states Contract Documents are complementary and what is required by one shall be as binding as if required by all. Sounds good so far, but
We have a client now who had an issue come up with another Architect who listed an order of precedence similar to what is recommended in the AIA A511, Guide For Supplemental Conditions, which went something like this:
"1.2.1.1 PRECEDENCE OF THE CONTRACT DOCUMENTS
The most recent issued Document takes precedence over previous issued forms of the same Document. The order of precedence is as follows with the highest authority listed first.
.1 The Agreement
.2 The Addenda
.3 Conditions of the Contract, Drawings, and Specifications shall have equal authority
Dont hold me to these facts, but the issue was something like this: The Architect had specified an Allowance for a portion of underground utility work and their connection to existing on-site utilities, since the full extent and exact location was unknown at the time of bidding. However, they also showed the scope of work on the drawings, indicating approximate locations of existing underground utilities, with the new connections. When they uncovered the existing utilities, low and behold they werent where they were shown on the drawings.
Now, the Agreement specifically stated as part of the requirements for the Work that site utility work as indicated on the Drawings was included in the Contract. Long story short, when the time came to do the work, because of that Contract clause, the Contractor felt he was only responsible for what was shown on the drawings, and he did not include the Allowance for that item in his proposal. As it turns out, he could not provide what was shown on the drawings so he wanted a change order to make it work. The Owner and Architect argued that because the drawings and specs are complementary, then the Contractor should have included the Allowance. But, thats the tricky part; the Contract specifically addressed that one issue referring to the drawings only, hence the discrepancy. It did not specifically state site utility work as indicated on the Drawings and in the Specifications.
Obviously, the Agreement can not address all the specifics of a project. It therefore includes the drawings and specs, and other Contract Documents, by reference, which defines the Work. What happens when the discrepancy is between the Agreement and the other documents? Was the Contractor correct, or the Owner?