Many good comments here. Most talk about an interview process and use a table of contents as a basis.
I know that many have a greatly enhanced table of contents, or a true checklist. I have a complete checklist that has essentially every question I need answered for every section in our office master. Some of these stop short of the complete discussion - if in some section I ask do you have X, Y or Z conditions, I then let the verbal part of the interview draw out those detailed answers and I write marginal notes that will need to be answered.
But there is more to it than just this. We have a process that has been in place since I set it up in the early 80s.
Every project manager/project architect knows that as soon as they are assigned a project, they need to inform me to schedule it. And must keep me updated of any changes to that schedule.
When they come to me to tell me this, that is when I print out the checklist and give it to them. They can then use it starting very early to keep track of decisions.
The schedule itself for specification purposes has due dates. Everything counts back from a production point.
We produce a draft project manual, including consultant’s sections, at the 75% point. I back up from that 3 weeks and have the checklist interview. And 2 weeks before the interview I have a ‘check in’ date which serves as a reminder that the interview is close.
At the checklist interview, they had me their original. I go through it with them, I mark it up as we talk. I put question marks where they need more information. At the end of the interview, it is handed back to them and they are given 3 days to answer questions or complete areas they did not complete.
When I get that from them, and they can’t take longer, the process is that if there are still questions or incomplete areas, those sections will not be included. The draft circulates to the owner/developer as well as internally and to all consultants since it also contains their sections. Right now, the typical draft goes at about 90 to 95% complete status.
And as to the checklist, its big. Currently runs 52 pages. Lots of white space to markup though, and it also asks for catalog cuts where I need those, and that they be marked for what is really needed. They are told be aggressive with a broad pen. X out what you don’t need/want. Not a small x by the title, cross the whole thing out.
Even interiors when they need to do a project manual use the same checklist, and I tell them, just toss the page if it does not have anything they are using.
No one has a problem with this, everyone uses it. Sure, some need special ‘encouragement’, but the process is understood as ‘required’.
When we move to the production of the final, I again have due dates. There is the final production date, there is a ‘cut off’ date that is 3 weeks before the final (anything give me after that date may not make it in - usually it does, but no promises) and there is a ‘check in’ date. The check in date states that on that day I need all the information to write the hardware completed - plans and door schedule. The rest of the information, comments, their review of the draft, etc. I want as a single package. They can give it to me No Earlier than the checkin date, No Later than the cutoff date. A single package, not a bunch of loose dribbling sheets and marks. The PA is required to compile comments from others into a single document of requirements. The PA is the one that is supposed to really know the project, its simply part of their responsibility.
All that happens, we go out the door, addenda are typically few and minor, and mostly drawings.
I have a timeline chart that I present about every 18 months or so that goes over all this.
Very important, I also have a web site calendar that includes each projects checkin, checklist, Draft publication, final checkin, final cut off, and final production dates. All PAs and PMs and principals have access to this, its used for project due date coordination. All know that if a due date conflicts with another or does not have 3 blank working days before or after it, its a conflict that needs to be resolved. Something has to give, and that’s how its presented. Of course sometimes it can’t be avoided, but this keeps it reasonable and its worked out ahead of time before promises are made. So true conflicts only come up 2 or 3 times a year.
When I set up the milestones and due dates for a project, it is put on that web based calendar, and the calendar notes include all the requirements. In addition, I email out the complete milestone listing at the time it is entered, and at any time that it is revised.
All specs for our DC and our Dallas office are written out of DC. For the interview process with Dallas, its done by email - which means their checklists and packages need to be much more complete, but its never been a hardship. What they collect for the spec is what they should be collecting anyway.
At the same time, I do materials research and act as the answer person as recommended above. if you are a resource as opposed to a data sink, you are welcomed into the team at all levels. Don’t become the person everyone has to give stuff to - sure, they really do have to do that, but become the person that is fully interactive with everyone.
William