**Author:** ![mark\_gilligan](https://avatars.discourse-cdn.com/v4/letter/m/f05b48/32.png) [@mark\_gilligan](https://forum.4specs.com/u/mark_gilligan)\
**Post date:** [March 19, 2009, 9:49pm UTC](https://forum.4specs.com/t/exterior-envelope-commissioning/1209/21 "2009-03-19T21:49:25Z")

</div>

“Stamped” means bearing the stamp and signature of the responsible licensed architect or engineer on the title page, and on every sheet of the documents, drawings, or specification…"

Did the Architect of Record really sign all pages in the specifications?

---

<div class="post-metadata">

**Author:** ![wayne\_yancey](https://yyz1.discourse-cdn.com/flex047/user_avatar/forum.4specs.com/wayne_yancey/32/228_2.png) [@wayne\_yancey](https://forum.4specs.com/u/wayne_yancey)\
**Post date:** [March 19, 2009, 10:33pm UTC](https://forum.4specs.com/t/exterior-envelope-commissioning/1209/22 "2009-03-19T22:33:13Z")

</div>

No.

As I mentioned at the beginning, the spec for these STFI projects were on 2 drawing sheets which have the stamp and signature same as other drawings. One of the general information sheets included a block of text that looks like a letter and included a similar statement to “The undersigned has provided building enclosure documents that in my professional judgment are appropriate to satisfy the requirements of RCW 64.55.005 through 64.55.090.”

---

<div class="post-metadata">

**Author:** ![Rliebing](https://avatars.discourse-cdn.com/v4/letter/r/c57346/32.png) [@Rliebing](https://forum.4specs.com/u/Rliebing)\
**Post date:** [March 20, 2009, 11:11am UTC](https://forum.4specs.com/t/exterior-envelope-commissioning/1209/23 "2009-03-20T11:11:38Z")

</div>

Granted the problem is not with ICC, Mark, but ICC has a great deal of influence and can reach a great many code officals and plans examiners. As with their manuals [that Ron mentuoned] and through education they can lay ground work for proper review using all submitted docuemtas.

There is an attempt to have ICC publish sn article but I am not sure where that stands. In any event. there will always be the strident code officals who does not understand and will do things for which there is authorization-- simply “that’s the way we do it, here”! But to acqeuiese to every different jurisidiction when you practice nationwide is a messy and very time consuming situation. For years many bleated for one code-- so now we have it but the locals insist on modifications so in reality we still have numerous codes. Yet there is still one way to produce contract documents that is time proven and has been realtively free of trouble [except where not in compliance]. Now it is a problem, not of technical nature but one of process, administration and who has what busninss machine for processing.

Surely it can be minimzed if not eliminated. There are wise and informed heads out there who need to prevail and bring along those we lack full insight and understanding.

---

<div class="post-metadata">

**Author:** ![khercenberg](https://yyz1.discourse-cdn.com/flex047/user_avatar/forum.4specs.com/khercenberg/32/104_2.png) [@khercenberg](https://forum.4specs.com/u/khercenberg)\
**Post date:** [March 20, 2009, 5:54pm UTC](https://forum.4specs.com/t/exterior-envelope-commissioning/1209/24 "2009-03-20T17:54:01Z")

</div>

Would it be feasible to print out a copy of the Whole Building Design Guide document (double sided, of course) and present it to the AHJ for reference? This would not as part of any project doucmentation which requires duplication or recording, but rather with the request that designers be allowed to include that document by reference on the Code compliance sheet in the Drawing Set. Perhaps this can be combined with a copy of the ABAA sample spec and other, similar documents.

A cover sheet explaining that A/E’s are not qualified to generate a commissioning plan, even if they are LEED AP’s, might help. To keep things in perspective, this document will presumably be used as the basis for contracts between Owners and their independent CxA’s, so referencing this general information gives Owners choices without locking them in to a specific ‘plan’. This may be a way to protect your clients as well as yourselves (and your fees). At least it may help establish some level of perspective for the AHJ since they presumably will otherwise have to review the lengthy documents that would ultimately be added to the drawings and would therefore require the review, recording, etc. AHJ’s are legally responsible for content they approve, so they need to be careful about reviewing plans that are not in keeping with the intent of the law.

Granted the WBDG document addresses numerous conditions, systems, components, and testing methods, at times referencing other documents. Granted this document is not project specific. Still, if the AHJ is willing to accept reference to this living document as being compliant with legal requirements “that detailed instructions have been provided in the construction documents” for exterior envelope commissioning, perhaps designers and Code Officials can both satisfy a vague law that neither entity asked for but still need to deal with.

My guess is that most reasonable AHJ’s would welcome an easy way to ensure that the laws are complied with while limiting their own exposure. I don’t know of any AHJ’s who have the time, resources, or expertise to conduct in-depth investigations into whether or not A/E’s have created commissioning plans that meet all of the requirements appropriate for each project.

With buy-in from the AHJ, these references might just allow everyone to rely on nationally recognized ‘standards’ while giving Owners some latitude when hiring CxA’s.

---

<div class="post-metadata">

**Author:** ![mark\_gilligan](https://avatars.discourse-cdn.com/v4/letter/m/f05b48/32.png) [@mark\_gilligan](https://forum.4specs.com/u/mark_gilligan)\
**Post date:** [March 20, 2009, 6:32pm UTC](https://forum.4specs.com/t/exterior-envelope-commissioning/1209/25 "2009-03-20T18:32:45Z")

</div>

I am of the opinion that non directive documents such as design guides do not belong in the contract documents. If you cannot agree on what is required you have no requirement.

Why not retain a commissioning consultant, possibly paid by the Owner, to produce the commissioning plan to be placed in the construction documents. Is this really any different than is done with other diciplines where the design professional lacks the necessary expertise.

---

<div class="post-metadata">

**Author:** ![jpjordan](https://avatars.discourse-cdn.com/v4/letter/j/67e7ee/32.png) [@jpjordan](https://forum.4specs.com/u/jpjordan)\
**Post date:** [March 23, 2009, 3:55pm UTC](https://forum.4specs.com/t/exterior-envelope-commissioning/1209/26 "2009-03-23T15:55:25Z")

</div>

I think one of the problems is that “commissioning” is different from “inspection and testing.” While they may seem the same, commissioning is an activity that takes place throughout the design and construction phases to verify that first the design (including drawings and specification) and then the construction is consistent with the design intent as stated in the Basis of Design. Inspection and testing for certain components is to ensure that inplace construction complies with construction documents generated by the design professional and code requirements established by the AJH. The differences may be subtle, but they are profound.

When the AHJ requires commissioning, I think they probably mean a more complete inspection and testing of the building envelope. Commissioning would be a more complex activity. The requirement set in place by one of the local AHJs indicates to me more that they really don’t understand what they want than anything else. Putting an indication that the owner/architect/contractor intends to comply with the requirements on the Drawings or in the Specs is really irrelevant.