The company I work for is building a new six million dollar facilty. We hired an architect to create the plans and write the specifications for this project. We invited four general contractors to bid the project. I am in charge of the construction process.
During the bidding process, I received a call from a supplier I know saying the architect rejected a substitution request because "The owner wants brand “x”.(This was news to me because no discussion ever took place) I told the supplier I would call the architect and get a further explantion.
I called the architect and was told this was a misunderstanding. He would allow the substitute.
I didn’t get a warm and fuzzy feeling when I got off the phone from the architect. It seemed like something was wrong.
So I called a friend who worked for a door/frame/hardware distributor in California. I asked him some questions about the specs and he told me to email him the door hardware specs.
He sent me an email telling me that hardware specification was probably written by a distributor or manufacturer trying to lock out the competition. There was only one manufacturer specified. And to top it off, the key system was exclusively tied to the local distributor.
I ask four general contractors to bid the project, I expected all phases to be competitivley bid. Or at least for the architect to tell me what items or phases of the work I wasn’t getting competetive pricing on.
I called my friend the hardware distributor and he said this “spec writing” was normal operating proceedure on private and public jobs.
Is this true?
I did further investingating of the specs and found out I wasn’t getting competetive prices on light fixtures, plumbing fixtures, some HVAC equipment, door hardware, and composite wall panels. There could have been more that I didn’t discover.
I found out in one instance that two manufactueres were listed in the specs, but both of the manufactueres were exclusively sold in my area by the same distributor.
I expected the architect to help me get competetive pricing. Is this an unrealistic expectation?
I told the owner of the company (my boss) what I found out and he came unglued.
We had a meeting with the architect and got equals inserted in the specifications before the job bid.
I am just a little frustrated to say the least.
Are architects to busy or lazy to write their own specs.
Do they need more education?
Are the distributors and manufactures taking them on so many golf outings and dinners, that they forget who writes them the check?
Please comment on this situation.